Packaging and Shipping of Steel Structures
Packaging of Unit Equipment
Container Loading
Project Construction Timeline
June 6, 2016: Completion of the first batch of prefabricated equipment
August 30, 2017: Topping-out of the paint shop building
December 12, 2017: Project start, unloading the container
December 16, 2017: Arrival of the first pretreatment process tank on-site
December 16, 2017 – February 28, 2018: On-site pre-assembly of tanks and Venturi components
March 1, 2018: Installation crew officially arrived on-site and began installation work
December 30, 2018: Main installation of paint shop process equipment completed
January 5, 2019: Partial energization of the paint shop began, starting commissioning work
January 20, 2019: Power-up and commissioning of painting robots
Installation, Testing, and Training for Automotive Coating Lines
Car bodies enter the electrophoretic coating tank for E-coating application
Electrophoretic paint maintained under 24-hour continuous agitation
Spray Showering in the Spray Tank
Spray Rinsing After Immersion Tank Exit
Paint Booth with Robotic Spraying
Training
Additional Details of the Current Automotive Coating Line
Car bodies enter the electrophoretic coating tank for E-coating application
Second-Floor Steel Platform for Pretreatment and E-Coating Operations
Panoramic View of the Pretreatment and E-Coating Booth Structure
Electrolyte Pump and Valve Assembly
Paper Band Filtration Machine
Oil-Water Separator
Phosphate Replenishment System
Plate-and-Frame Filter Press Equipment
Nitric Acid Cleaning System
Magnetic Filtration System
Downstream Dust Protection, Elevators, Preheating Zone, Insulation Zone, and Forced Cooling Chamber
Robotic Sealant Application
Automotive Painting Robot
Topcoat Inspection of Painted Vehicles
Electrical Control Equipment for the Complete Vehicle Coating System
Ultrafiltration Module